Hitting the ground running on Mainstream’s new warehouse

Mainstream Warehouse

Hitting the ground running on Mainstream's new warehouse

Category

Industrial

Client

KiwiRail

Location

Wellington

Budget

$2.7M

Category
Industrial
About This Project

Design and construction of a new 2,500m² new facility for Mainstream Limited, comprising a 2000m² warehouse, rail sliding into the building area, loading area and 120m² single storey office space. Kiwirail approached Arrow at the end of February with nothing more than concept sketches, an outline specification and a geotechnical report, and challenged us to deliver the entire facility by the beginning of September – just seven months for full design and construction.

 

Unique Aspects

Despite challenging ground conditions, gale force winds, constant rain and increased scope, the team were able to hand over the completed shed in just seven months – an incredible result.